House Extension and Electrical Work Scope of Works Site survey, drawings & planning (architect measurements, concept plans, planning/Building Reg applicatio...
Adding a new room to a UK house brings electrical work into scope automatically — the new space needs its own circuits or extensions of existing ones, and the work is notifiable under Part P of the Building Regulations. Typical electrical cost on a single-storey rear extension runs £2,500–£6,500 on top of the build cost itself; for a two-storey extension or a loft conversion, expect £4,000–£9,000.
The electrician should be involved from first-fix — running cables before plaster — through second-fix (sockets, switches, lights) and on to final test and Part P certification. Trying to retrofit electrics after plastering is an expensive mistake.
What's typically in scope
- Lighting circuit extension — new pendants, downlights or LED panels, switched from sensible locations. £150–£300 per light point.
- Sockets and dedicated circuits — typically a new ring main if the extension is over 25 m², plus dedicated circuits for kitchen appliances if it's an open-plan kitchen-diner.
- Consumer unit upgrade — older consumer units (rewireable fuse box, or split-load without RCDs) need replacing to a modern 18th edition unit. £450–£900 supplied and fitted.
- Smoke and heat detectors — Building Regs require interconnected mains-powered alarms in any extended dwelling. £350–£700 for a typical two-bed extension.
- Outdoor power and lighting — security lights, garden sockets, EV charger feeds. From £150 for a basic outdoor light to £900+ for an EV charge point.
Typical UK costs
| Job | Typical price (extension scope) |
|---|---|
| Single-storey rear extension (4×4 m, basic spec) | £2,500–£4,500 |
| Open-plan kitchen-diner extension (with appliances) | £3,500–£6,500 |
| Loft conversion (1–2 bedrooms + bathroom) | £3,000–£6,000 |
| Two-storey side extension (full rewire of extended areas) | £4,500–£9,000 |
| Consumer unit upgrade (18th edition) | £450–£900 |
| Part P certification + EICR for the works | £200–£400 |
Estimates assume an experienced extension electrician working with the builder; main-dealer or premium fit-out specialists charge 30–50% more.
Part P and Building Regulations
Any new circuit, consumer unit replacement, or work in special locations (kitchens, bathrooms, gardens) is notifiable. There are two paths:
- Use a Part P registered electrician (NICEIC, NAPIT, ELECSA scheme members) who self-certifies and arranges the certificate via their scheme. Easier and cheaper — most extension electricians are scheme members.
- Notify Building Control directly and have them inspect, with a non-registered electrician doing the work. Adds £300–£600 in inspection fees and slows things down.
The Part P certificate is essential when you sell — solicitors will ask for it and an absence creates a price-reducing question on the sale.
First-fix, second-fix, final test
Three distinct stages with different timing requirements:
- First-fix — runs cables before plaster, sets back boxes, drops feeds for sockets and switches. Has to happen after plumbing first-fix and before plastering. 3–5 days for a typical extension.
- Second-fix — installs sockets, switches, light fittings, smoke alarms after plastering and decoration. 2–3 days.
- Final test and certificate — half a day of testing, paperwork, and Part P notification.
Things people often miss
- Existing consumer unit capacity — older split-load CUs may not have spare ways for new circuits. A unit upgrade often becomes mandatory and should be priced from day one.
- Earthing arrangement — some older houses have TT earthing (rod-based); modern installations almost always require TN-S or TN-C-S. Upgrading the earthing arrangement adds £250–£600 and may need DNO involvement.
- Cable routes — running cables from the new extension back to the consumer unit can mean lifting flooring or chasing walls in the existing house. Plan route choices early to minimise disruption.
- Smart-home and CAT6 — first-fix is the cheapest moment to run data cables, smart-switch loops, and electric blind feeds. Adding them later means lifting newly-laid floors. Decide spec before the plaster goes up.
- EV charger — even if you're not buying an EV now, dropping a 16 mm² cable on the first-fix budget for £300–£500 saves a £1,500 retrofit later.
Frequently asked questions
Do I need a separate electrician or can my builder handle it?
Most builders will subcontract to a Part P registered electrician — they don't usually self-perform electrical work. Either source your own (often slightly cheaper) or let the builder include it in their package. Either way, the electrician must be Part P registered for the certificate.
Will my consumer unit need replacing?
Probably yes, if it's pre-2008 (rewireable fuses, or a split-load without RCDs in every circuit). Modern Building Regs and the 18th Edition Wiring Regs require RCD or AFDD protection on most circuits. Budget £450–£900 supplied and fitted.
How long does the electrical work add to an extension build?
Roughly 1 week first-fix + 2–3 days second-fix + half a day for testing. Total ~7–10 working days spread across the build, fitted around plumbing, plastering and decoration.
Do I need a new ring main for an extension?
For extensions under 20 m², extending the existing ring main is usually fine. For larger extensions or open-plan kitchen-diners with multiple appliances, a new ring main avoids overloading the original. Your electrician will assess based on layout and load.
What happens if Part P isn't certified?
Building Control can refuse completion certificate, and your buyer's solicitor will flag it as a defect on sale. Retrospective certification costs £400–£900 and means an EICR-style inspection plus any remedial work — much more expensive than doing it right the first time.
Can I run my own data cables alongside the electrician's first-fix?
Possible if you're comfortable with low-voltage data work, but coordinating with the electrician to run them in the same channels saves both time and money. Most extension electricians will run CAT6 alongside power cables for £30–£60 per data point.
Want a local pro to handle this? A Part P registered electrician with extension experience is essential. Don't try to add electrical work to a builder who isn't electrically qualified — Part P certification is non-negotiable for resale.
This guide was written with AI assistance and is intended for general information only. Prices are estimates based on UK averages and may vary by region. Always get at least three quotes and consult a qualified professional before starting any work.
